Update on St Kizito Ward, by John Mwanza
Works at St. Kizito ward are progressing very well. About 70% of the whole project has been done in 50 working days. Replacing the asbestos roofing with iron sheet at Kizito building is done, casting of Terrazzo is almost done, with only skirting and casting of Terrazzo floor in the main corridor (between Kizito and Mukasa) remaining. Construction works are at Nurses bay and construction of extended staff side wards. This project is being supported by the Medical Support Group and Wilde Ganzen Foundation, the Netherlands. Mr. Chungu Mutale a dedicated project manager is the supervisor for this project and Construction for Africa is the contractor on site.
Photos below:1. works at nurses’ bay, 2. extension works of staff side wards.